Project Duration
Stipulated Date of Commencement
September 21 2018
Stipulated Date of Completion /
Likely Date of Completion December 21 2018
Likely Date of Completion December 21 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,292,381.00
Awarded for
₹ 9,083,500.00
Project highlights
The scope of work includes:
1) Supply, installation, testing & commissioning of 33 KV, 3CX400 sq. mm, underground armoured cable – 4078 meters.
2) Supply, installation, testing & commissioning of 11 KV, 3CX300 sq. mm, underground armoured cable – 108 meters.
3) Dismantling of HT/LT overhead lines and Installation of new 100kVA distribution transformer centre.
Contractors
M/s. Consistent Engineers
Consultants
M/s. Nitin Arolkar
See Similar Projects
Bridge Across St. Inez Creek on 18th June Road, Panaji
View Project
Construction of Road Bridge at Balli in Quepem Constituency on Balli – Fatorpa MDR Road at Balli in Quepem.
View Project
Acoustic work for Multipurpose Hall.
View Project