Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion April 24 2014
Likely Date of Completion April 24 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,889,214.00
Awarded for
₹ 12,222,932.73
Project highlights
The work includes construction of road from NH-4A to Miraculous Cross Church. Length of Road -700m, 25mm thick Asphalt Concrte ,50mm thick DBM ,50mm thicj BM along with Crash Barrier .
Contractors
M/s.Ritesh Developers
Consultants
M/s.Kashec Engineers Pvt Ltd .