Project Duration
Stipulated Date of Commencement
June 19 2021
Stipulated Date of Completion /
Likely Date of Completion August 18 2021
Likely Date of Completion August 18 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,408,613.00
Awarded for
₹ 1,365,210.00
Project highlights
Repair and Maintenance Works at Assonora Sports Complex.
Contractors
M/s. Nikhil Kulkarni and Co.
Consultants
M/s. Gurudutt Sanzgiri