Project Duration
Stipulated Date of Commencement
January 09 2023
Stipulated Date of Completion /
Likely Date of Completion January 17 2023
Likely Date of Completion January 17 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,640,591.00
Awarded for
₹ 921,000.00
Contractors
M/s. Harish Iron Store
Consultants
M/s. Ameet Sukhthankar Architects & Interior Designers.