Project Duration
Stipulated Date of Commencement June 15 2018
Stipulated Date of Completion /
Likely Date of Completion
June 30 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,204.00
Awarded for ₹ 45,312.00

Project highlights

The scope of work invloves installation of decorative street light poles along with the cabling work and providing foundations for street lights.

 
Gallery Image
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Construction of bridge at Paikul, Sattari-Goa

View Project
Similar Project

Repairs and Resurfacing of PANAJI ROADS

View Project
Similar Project

Construction of Minor Bridge across river Tar at Mapusa, Goa on MDR-14

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.