Project Duration
Stipulated Date of Commencement
August 28 2006
Stipulated Date of Completion /
Likely Date of Completion October 11 2006
Likely Date of Completion October 11 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 179,398.00
Awarded for
₹ 205,946.53
Contractors
M/s. Sandesh C. Naik
Consultants
In-house (GSIDC)