Project Duration
Stipulated Date of Commencement
June 20 2008
Actual Date of Completion
December 31 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rs.3,63,53,407.64
Awarded for
₹ 52,100,720.15
Final Cost of Project
₹ 41,293,180.00
Project highlights
Swimming pool (25.40 x 20.40 mts.), with depth varying from 1.098 to 1.824 mts. The size of Baby pool is 5.40 x 5.61 mts. Changing rooms for ladies and gents. Shower rooms for ladies and gents, Office,Common room, adequate toilet facilities, Ample parking facilities, Soft landscaping in the premises with illumination.
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd., M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. M. S. Suctancar, M/s. M. S. Suctancar
See Similar Projects
Infrastructure works for Sanjay Centre for Special Education at Bogda, Vasco – Electrical, Lift and Fire Fighting Works
View ProjectReconstruction of Government Primary School at Falwada, Cudnem in Bicholim Taluka- Civil, plumbing & electrical works.
View ProjectDevelopment of a Taluka Sports Complex at Borimol, Quepem, Goa
View Project