Project Duration
Stipulated Date of Commencement March 27 2007
Stipulated Date of Completion /
Likely Date of Completion
March 26 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 54,371,959.00
Awarded for ₹ 69,139,000.00
 
Gallery Image
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Construction of Swimming pool at Ponda Sports Complex – Additional works such as Jogging Track, Road, Compound wall, Security Cabin etc.

100% completed
 
Project Duration
Stipulated Date of Commencement February 12 2009
Stipulated Date of Completion /
Likely Date of Completion
May 11 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 50,71,379.00
Awarded for ₹ 47,00,750.52
 
Contractors
Contractors
M/s. Rohit Equipments
Consultants
Consultants
M/s. Datta Kare Associates
Similar Projects

See Similar Projects

Similar Project

Repairs/Upgradation and Maintenance of Govt. Schools in the State of Goa -Civil, Plumbing and Electrical Works (Package XI) Salcete Taluka

View Project
Similar Project

Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Construction of Government Primary school at Vasantnagar, Sankhali in Bicholim Taluka.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.