Project Duration
Stipulated Date of Commencement February 11 2007
Actual Date of Completion January 25 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 51,241,559.00
Awarded for ₹ 71,828,955.90
Final Cost of Project ₹ 71,288,337.00
 
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Consultants
M/s. Mahimtura Consultants Pvt. Ltd., M/s. Mahimtura Consultants Pvt. Ltd.
 