Project Duration
Stipulated Date of Commencement
January 05 2022
Stipulated Date of Completion /
Likely Date of Completion January 14 2023
Likely Date of Completion January 14 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 25,108,748.16
Awarded for
₹ 28,284,599.49
Project highlights
Construction of sewage Treatment Plant
Contractors
M/s.Indage Development Construction Pvt. Ltd.
Consultants
M/s. FP Project Management.
See Similar Projects
Procurement of hospital furniture for new ward of plastic surgery at Goa Medical College & Hospital, Bambolim, Goa.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, and RMDs under Directorate of Health Services in North Goa –S.H : Maintenance/Renovation work of Community Health Centre at Bicholim – AMC for 200kVA Transformer at CHC Bicholim for 3 years (2019-2022).
View Project
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa – Civil and plumbing works.
View Project