Project Duration
Stipulated Date of Commencement
August 02 2019
Stipulated Date of Completion /
Likely Date of Completion August 15 2023
Likely Date of Completion August 15 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 64,676,198.06
Awarded for
₹ 73,281,322.55
Project highlights
Project involves construction of G+3 structure to provide rest house for the retired/ex service army officers on vacations.
The rest house will provide 12 guest rooms with other amenities .Total Built up area of the project is 849.84sqm
Contractors
M/s. Shreejikrupa Buildcon Ltd.
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
External electrical works at area around new Library Building and Power supply to new Library building at GMC Complex.
View Project
Air Conditioning and Ventilation System
View Project
Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for the Schindler make elevators installed at Medicine Ward Block for a period of one year (2020-2021).
View Project