Project Duration
Stipulated Date of Commencement
August 02 2019
Stipulated Date of Completion /
Likely Date of Completion August 15 2023
Likely Date of Completion August 15 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 64,676,198.06
Awarded for
₹ 73,281,322.55
Project highlights
Project involves construction of G+3 structure to provide rest house for the retired/ex service army officers on vacations.
The rest house will provide 12 guest rooms with other amenities .Total Built up area of the project is 849.84sqm
Contractors
M/s. Shreejikrupa Buildcon Ltd.
Consultants
M/s. Rahul Deshpande & Associates