Project Duration
Stipulated Date of Commencement February 17 2024
Stipulated Date of Completion /
Likely Date of Completion
February 16 2025
Status
2%
Completed
Cost (₹)
Estimated at ₹ 20,957,778.77
Awarded for ₹ 22,641,244.50

Project highlights

The project is GH structure with Diagnotics and Out Patient Department, Casualty Room; 1 & 2 Treatment Room, Laboratory, Pharmcay, Immunization room and Sanitory accommodation.

 
Gallery Image
Contractors
M/s A. Y. Gulumkar
Gallery Image
Consultants
M/s. Datta Kare Associates
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of existing Rural Medical Centre at Collem, Dharbandora – Civil, Plumbing, Electrical, Lift, HVAC and Fire Fighting works

View Project
Similar Project

Construction of 500 Bedded District Hospital At Margao, Goa – Additional Fire Fighting Work

View Project
Similar Project

Construction of New Premises for Community Health Centre at Tuem, Pernem, Goa: Balance Civil & Plumbing works.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.