Project Duration
Stipulated Date of Commencement
August 02 2021
Stipulated Date of Completion /
Likely Date of Completion March 31 2024
Likely Date of Completion March 31 2024
Status
95%
Completed
Cost (₹)
Estimated at
₹ 2,444,709.00
Awarded for
₹ 2,163,530.00
Project highlights
The work consists of additional requirements, such as hooters, supression system, etc, as asked by the Directorate of Fire and Emergency Services.
Contractors
M/s. Antifire Systems,
Consultants
M/s. KICONS Limited