Project Duration
Stipulated Date of Commencement February 11 2010
Stipulated Date of Completion /
Likely Date of Completion
July 10 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 11,877,563.00
Awarded for ₹ 9,939,420.00
 
Gallery Image
Contractors
M/s. Knchan Associates
Gallery Image
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Construction of Panchayat Building at V.P. Mayem – Vaiguinim, Bicholim Taluka (Balance Works)

View Project
Similar Project

Construction of a New Wholesale Fish Market at Margao (Phase I – Site Development work).

View Project
Similar Project

Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme 2013 – Construction of Panchayat Building at Usgao with an integrated Community Hall

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.