Project Duration
Stipulated Date of Commencement
February 11 2010
Actual Date of Completion
November 15 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,877,563.00
Awarded for
₹ 9,939,420.00
Contractors
M/s. Knchan Associates
Consultants
M/s. Intertek Architects & Consultants Pvt. Ltd.