Project Duration
Stipulated Date of Commencement
January 08 2006
Stipulated Date of Completion /
Likely Date of Completion February 15 2006
Likely Date of Completion February 15 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 875,750.00
Awarded for
₹ 693,650.00
Project highlights
Providing power supply to the new Library building from the transformer near Mortuary buidlign, GMC Complex, procuring and laying of cable.
Contractors
M/s. Ohm Engineers
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD