Project Duration
Stipulated Date of Commencement
December 25 2010
Actual Date of Completion
June 07 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 55,35,000.00
Awarded for
₹ 6,420,000.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.