Project Duration
Stipulated Date of Commencement November 12 2014
Actual Date of Completion June 30 2015
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,582,490.00
Awarded for ₹ 4,199,999.00
 
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Inhouse
 