Project Duration
Stipulated Date of Commencement February 22 2008
Stipulated Date of Completion /
Likely Date of Completion
August 21 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 10,780,533.00
Awarded for ₹ 9,700,990.00

Project highlights

Land filling and construction of retaining wall

 
Gallery Image
Contractors
M/s. Rohit Equipments
Gallery Image
Consultants
M/s. Vijaykumar Sawant Associates
 
Similar Projects

See Similar Projects

Similar Project

Book Cutting Machine.

View Project
Similar Project

Stage Drapery work

View Project
Similar Project

Upgradation of existing Neura village Panchayat ghar building for V.P.Neura under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) scheme.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.