Project Duration
Stipulated Date of Commencement
February 22 2008
Stipulated Date of Completion /
Likely Date of Completion August 21 2008
Likely Date of Completion August 21 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,780,533.00
Awarded for
₹ 9,700,990.00
Project highlights
Land filling and construction of retaining wall
Contractors
M/s. Rohit Equipments
Consultants
M/s. Vijaykumar Sawant Associates