Project Duration
Stipulated Date of Commencement
February 01 2014
Stipulated Date of Completion /
Likely Date of Completion March 17 2014
Likely Date of Completion March 17 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,077,369.00
Awarded for
₹ 2,229,999.00
Project highlights
HVAC Works.
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.