Project Duration
Stipulated Date of Commencement
March 03 2014
Stipulated Date of Completion /
Likely Date of Completion April 17 2014
Likely Date of Completion April 17 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,627,620.00
Awarded for
₹ 4,622,904.00
Project highlights
Fire Fighting Works.
Contractors
M/s. IFEX Technologies (I) Pvt. Ltd.
Consultants
M/s. KICONS Pvt. Ltd.
See Similar Projects
Interior works.
View Project
Telephone Exchange and UPS (Part A- UPS work)
View Project
Alteration & modification works to Commercial tax office at Altinho
View Project





