Project Duration
Stipulated Date of Commencement February 08 2015
Stipulated Date of Completion /
Likely Date of Completion
January 01 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rs.19,93,04,971.61
Awarded for ₹ Rs.22,98,73,257.00

Project highlights

The building is G+1 RCC framed structure with a mezzanine floor having a Football ground, which is housed on a net area of 27,473.48 Sqm, with a total built up area of 5,400.20 sqm GROUND FLOOR • Boxing ring with toilet for Ladies & Gents.
• Panchayat Office with Cabin for Sarpanch & Secretary, a Conference Room, Record Room, General Staff and Service room along with toilet facilities.
• Doctor’s & Veterinary Doctor’s Room having individual toilets.
• Post Office, Shops – 13 nos. with common toilet facilities.
• Two Lifts with capacity of 8 passengers in each. FIRST FLOOR :• Badminton Court as per standard size, Reading Room, Gymnasium, Cafeteria with Pantry Room for Indoor Games like Chess, Carrom, etc., Toilet facilities for ladies and gents
• A Multipurpose Hall [with capacity of 300 people] with Green Room for Ladies & Gents along with Mezzanine Floor for Multipurpose Hall having Kitchen, Dining, Kitchen Store & Toilets.

 
Gallery Image
Contractors
M/s. M. Venkata Rao Infra Projects Pvt. Ltd.
Gallery Image
Consultants
M/s. Banaji & Associates
 

Sub Works

This project involved 3 sub works. The details of the same available below

1

Construction of Multipurpose Hall and office building for Village Panchayat, Salvador do Mundo – Phase I Land Development.

100% completed
 
Project Duration
Stipulated Date of Commencement February 27 2009
Stipulated Date of Completion /
Likely Date of Completion
August 26 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 12,541,225.00
Awarded for ₹ 10,902,411.00

Project highlights

Construction of retaining wall, compound wall and land filling etc.

 
Contractors
Contractors
M/s. Rohit Equipments
Consultants
Consultants
M/s. Banaji & Associates
2

Construction of Multipurpose Hall and Office Building for V.P.Salvador Do Mundo – Additional works.

100% completed
 
Project Duration
Stipulated Date of Commencement March 04 2019
Stipulated Date of Completion /
Likely Date of Completion
January 03 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 26,785,068.56
Awarded for ₹ 28,035,272.68

Project highlights

Construction of compound wall, ground & concrete road.

 
Contractors
Contractors
M/s. Gore Infrastructure
Consultants
Consultants
M/s. Banaji & Associates.
3

INTERIOR WORKS

100% completed
 
Project Duration
Stipulated Date of Commencement December 30 2017
Stipulated Date of Completion /
Likely Date of Completion
March 29 2018
Status
100%
Completed
Cost (₹)
Estimated at ₹ Rs.1,17,90,772.00
Awarded for ₹ Rs.1,03,92,743.60

Project highlights

Providing of Office Furniture, Gym equipments, aluminium glazing work, Signages etc.

 
Contractors
Contractors
M/s. Amardeep Designers India Pvt. Ltd.
Consultants
Consultants
M/s. Banaji & Associates
Similar Projects

See Similar Projects

Similar Project

Construction of Library Building at Margao.

View Project
Similar Project

Electrical.

View Project
Similar Project

Removal of Rubbish/Debris and leveling of parking area

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.