Project Duration
Stipulated Date of Commencement
June 29 2007
Stipulated Date of Completion /
Likely Date of Completion April 28 2008
Likely Date of Completion April 28 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 21,659,145.00
Awarded for
₹ 24,825,361.12
Project highlights
The total built-up area is 1,507.49 sq. m. The ground floor of the market houses stalls of fish and vegetable vendors. Also, there is provision for a bank with toilet, post office, electricity office, health centre with toilet, shops, etc.
The first floor consisst of Panchayat office with cabins for the Sarpanch, Secretary, conference hall and gymnasium. The second floor consists of a multipurpose hall with stage, green rooms and toilets.
Contractors
M/s. M. B. Kinlekar
Consultants
M/s. Datta Kare Associates
See Similar Projects
Upgradation of Infrastructure in the rural areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme , 2013 -Panchayat Ghar For Village Panchayat Sarzora – Salcete – Loose Furniture works
View Project
Additional Electrical work (Package 2)
View Project
Air Conditioning work.
View Project