Project Duration
Stipulated Date of Commencement March 08 2019
Stipulated Date of Completion /
Likely Date of Completion
March 07 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 194,696,690.00
Awarded for ₹ 194,177,475.00

Project highlights

The project comprises of a Grand Auditorium – 740 Seater Capacity. Ground Floor consists of a Cafetaria, Pantry, Green rooms for ladies, gents and VIP, Loading & unloading deck, Administration Section, Ticketing & information counter, Store rooms, Toilets for Handicapped, Ladies and Gents etc.First Floor shall comprise of Mini lecture halls, Classrooms – 03nos, Library, Pantry, VIP rest room for ladies and gents, Rehearsal room, Store rooms, AHU rooms – 2nos., Handicapped toilets, ladies & gents toilets etc. Second Floor shall comprise of a Black box – 120 seating capacity, Pantry, Musical Classrooms – 4nos, Toilets for Handicapped, Ladies and Gents, Changing rooms, AHU rooms – 2nos., Store rooms etc.

 
Gallery Image
Contractors
M/s. Narayan Kumar Infrastructure (I) Pvt. Ltd
Gallery Image
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

CCTV work.

View Project
Similar Project

Construction of New Building for Goa Board of Secondary and Higher Secondary Education, Porvorim-Goa – Interior & Furniture works

View Project
Similar Project

CPOE switches

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.