Project Duration
Stipulated Date of Commencement January 24 2014
Stipulated Date of Completion /
Likely Date of Completion
July 23 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 48,097,756.00
Awarded for ₹ 54,788,911.15

Project highlights

· The project includes Construction of Jogger’s Park in a plot of Area 30821 Sqm located at Dabolim, Mormugao Taluka at South Goa District.

 
Gallery Image
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Gallery Image
Consultants
M/s. Casta Engineers Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Upgradation of Existing Panchayat Building in survey no.372/5 for Borim Panchayat at Borim, Ponda Goa.

View Project
Similar Project

Construction of Multiplex.

View Project
Similar Project

Supply, Installation, Testing and Commissioning of street light poles and fixtures along with allied electrical works for the stretch from Odxel junction to GMC

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.