Project Duration
Stipulated Date of Commencement
February 27 2014
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
90%
Completed
Cost (₹)
Estimated at
₹ 67,035,071.00
Awarded for
₹ 50,042,083.80
Project highlights
Supplying light fixtures and electrical equipments for substation of dental phase II building.
Contractors
M/s. Power & Instrumentation (Guj.) Ltd.
Consultants
M/s. FP Project Management