Project Duration
Stipulated Date of Commencement
September 19 2022
Stipulated Date of Completion /
Likely Date of Completion June 18 2023
Likely Date of Completion June 18 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 55,590,132.35
Awarded for
₹ 53,712,065.00
Project highlights
Hostel rooms with attached toilets, Guest room, Dinning, Library, open courtyard, indoor room, recreationla facilities, Laundary room, parking facilities etc…
Contractors
M/s A.R. Construction
Consultants
M/s Amit Sukthankar
See Similar Projects
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Pernem Taluka: Package – V (GPS Tiwade Dhargal, GPS Chandel, GPS Madkai Ozari, GPS Varkhand, GPS Bhatpavni, GPS Patradevi, GPS Fakirpata Torse, GPS Tulaskarwadi)
View Project
Repairs/Upgradation and Maintenance of Government Primary Schools in the State of Goa Dharbandora Taluka –Sanguem taluka (GPS Chimutwada, GPS Wadem, GPS Mirabag, GPS Vichundrem)
View Project
Repairs/ upgradation of School in the state of Goa Package -V (Quepem & Canacona Taluka)
View Project