Project Duration
Stipulated Date of Commencement
September 19 2022
Stipulated Date of Completion /
Likely Date of Completion June 18 2023
Likely Date of Completion June 18 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 55,590,132.35
Awarded for
₹ 53,712,065.00
Project highlights
Hostel rooms with attached toilets, Guest room, Dinning, Library, open courtyard, indoor room, recreationla facilities, Laundary room, parking facilities etc…
Contractors
M/s A.R. Construction
Consultants
M/s Amit Sukthankar