Project Duration
Stipulated Date of Commencement
October 05 2022
Stipulated Date of Completion /
Likely Date of Completion July 31 2024
Likely Date of Completion July 31 2024
Status
65%
Completed
Cost (₹)
Estimated at
₹ 66,593,996.00
Awarded for
₹ 69,796,309.81
Project highlights
Hospital Building with wards, consulting rooms, farmacy, and other amenities.
Contractors
M/s. K. G. Thomas
Consultants
M/s. Vaishali Pednekar Associates