Project Duration
Stipulated Date of Commencement March 09 2019
Actual Date of Completion March 08 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,873,996.00
Awarded for ₹ 32,612,575.32

Project highlights

Construction of school building with entire civil, plumbing & electrical works

 
Contractors
M/s. Race Constructions
Consultants
M/s Bhaskar Wagle Associates
 

See Similar Projects

Infrastructure works for Sanjay Centre for Special Education at Bogda, Vasco.

View Project

Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka

View Project

Construction of Government Primary School at Dattagad, Bethora, Ponda Goa- Civil, Plumbing & Electrical works

View Project