Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion March 08 2020
Likely Date of Completion March 08 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,873,996.00
Awarded for
₹ 32,612,575.32
Project highlights
Construction of school building with entire civil, plumbing & electrical works
Contractors
M/s. Race Constructions
Consultants
M/s Bhaskar Wagle & Associates