Project Duration
Stipulated Date of Commencement
July 15 2019
Actual Date of Completion
Status
100%
Completed
Cost (₹)
Estimated at
₹ 221,496,176.00
Awarded for
₹ 204,287,929.54
Project highlights
False ceiling, interior, furniture signage, security installation and other miscellaneous works
Contractors
M/s. Siddhi Construction,
Consultants
M/s. LKS India Pvt. Ltd.,