Project Duration
Stipulated Date of Commencement April 10 2015
Actual Date of Completion March 31 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 21,184,374.00
Awarded for ₹ 16,708,003.14
Final Cost of Project ₹ 16,478,990.00
 
Contractors
M/s. Shalaka Infra Tech (I) Pvt. Ltd.
Consultants
M/s. KICONS Limited
 