Project Duration
Stipulated Date of Commencement
February 09 2015
Stipulated Date of Completion /
Likely Date of Completion June 08 2015
Likely Date of Completion June 08 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 18,865,681.00
Awarded for
₹ 15,790,525.00
Project highlights
The project involved supply of modular furnitures, kitchen equipments etc for Girls hostel at GMC
Contractors
M/s. Classic Interiors
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD