Status
100%
Completed
Contractors
Consultants
Sub Works
This project involved 4 sub works. The details of the same available below
1
Civil,Plumbing,Electrical,Fire fighting, Lift and HVAC works.
100% completed
Project Duration
Stipulated Date of Commencement
November 05 2014
Stipulated Date of Completion /
Likely Date of Completion May 06 2020
Likely Date of Completion May 06 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 292,919,099.00
Awarded for
₹ 357,020,022.60
Final Cost of Project
₹ 416,060,328.31
Project highlights
New building for the CHC with 80 bed capacity
Contractors
M/s. MVR Infra Projects Pvt. Ltd
Consultants
M/s. Saolapurkar Associates
2
False Ceiling, Acoustical Paneling and Miscellaneous Works
100% completed
Project Duration
Stipulated Date of Commencement
January 24 2019
Stipulated Date of Completion /
Likely Date of Completion February 01 2020
Likely Date of Completion February 01 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,414,718.00
Awarded for
₹ 14,597,625.70
Final Cost of Project
₹ 14,456,281.00
Project highlights
False Ceiling, Acoustical Paneling and Miscellaneous Works
Contractors
M/s. Knchan Associates
Consultants
M/s. Saolapurkar Associates
3
Additional Miscellaneous Works
100% completed
Project Duration
Stipulated Date of Commencement
June 24 2022
Stipulated Date of Completion /
Likely Date of Completion February 15 2023
Likely Date of Completion February 15 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,066,766.80
Awarded for
₹ 13,903,408.51
Project highlights
Additional internal and external works in the new CHC premises
Contractors
M/s. Sri Srinath Infra
Consultants
M/s. Saolapurkar and Associates,
4
Supply, Installation, Testing and Commissioning of Hospital Furniture, Kitchen Equipment and Interior works.
100% completed
Project Duration
Stipulated Date of Commencement
December 27 2021
Stipulated Date of Completion /
Likely Date of Completion February 28 2023
Likely Date of Completion February 28 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 31,988,644.00
Awarded for
₹ 29,921,594.28
Project highlights
Providing Hospital Furniture, Kitchen Equipment and other Interior works
Contractors
M/s. Concept Creators,
Consultants
M/s. Saolapurkar and Associates,
See Similar Projects
Additional 5 sheds awarded to the same Contractor