Project Duration
Stipulated Date of Commencement
January 23 2019
Actual Date of Completion
March 10 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 26,885,072.00
Awarded for
₹ 19,212,281.50
Final Cost of Project
₹ 17,885,831.00
Project highlights
Projects involves providing interior furniture and readaymade furniture
Contractors
M/s. T. S. Mistry,
Consultants
M/s. UCJ Architecture & Environment,