Project Duration
Stipulated Date of Commencement January 23 2019
Actual Date of Completion March 10 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 26,885,072.00
Awarded for ₹ 19,212,281.50
Final Cost of Project ₹ 17,885,831.00

Project highlights

Projects involves providing interior furniture and readaymade furniture

 
Contractors
M/s. T. S. Mistry,
Consultants
M/s. UCJ Architecture & Environment,
 