Project Duration
Stipulated Date of Commencement
May 09 2012
Stipulated Date of Completion /
Likely Date of Completion April 02 2013
Likely Date of Completion April 02 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 53,472,844.68
Awarded for
₹ 46,135,000.00
Contractors
M/s. Kaydee Enterprises
Consultants
M/s. Effective Architectural Services