Project Duration
Stipulated Date of Commencement
November 18 2010
Stipulated Date of Completion /
Likely Date of Completion August 17 2011
Likely Date of Completion August 17 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,835,300.00
Awarded for
₹ 1,917,880.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Effective Architectural Services