Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion June 25 2007
Likely Date of Completion June 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,671,482.00
Awarded for
₹ 18,007,783.00
Contractors
M/s. MGI (I) Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
See Similar Projects
Extension of R.M.O Hostel at Goa Medical College and Hospital, Bambolim, Goa S.H.: Supply, Installation, Testing and Commissioning of 11KV 4 Way outdoor type RMU and other allied works
View Project
Replacement of lifts at Goa Medical College including comprehensive AMC at Bambolim, Goa
View Project
Air conditioning work
View Project





