Project Duration
Stipulated Date of Commencement
March 26 2007
Stipulated Date of Completion /
Likely Date of Completion June 25 2007
Likely Date of Completion June 25 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,488,696.00
Awarded for
₹ 8,161,350.00
Contractors
M/s. MGI (I) Pvt. Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.