Project Duration
Stipulated Date of Commencement January 25 2007
Stipulated Date of Completion /
Likely Date of Completion
October 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 29,518,019.00
Awarded for ₹ 31,090,000.00
 
Gallery Image
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 