Project Duration
Stipulated Date of Commencement
December 22 2010
Stipulated Date of Completion /
Likely Date of Completion January 22 2011
Likely Date of Completion January 22 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,677,500.00
Awarded for
₹ 2,677,500.00
Contractors
M/s. KGS Microsystems
Consultants
In-house (GSIDC)