Project Duration
Stipulated Date of Commencement
Stipulated Date of Completion /
Likely Date of Completion
March 08 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 22,573,604.66
Awarded for ₹ 20,444,375.59

Project highlights

(i) Ground floor Electricity Dept of 7.00×6.23mt.
(2) Gym of 7.00 x 9.46 mts.
(3) There is one shop on Ground floor.
(4) Eight shops with area 3.00×7.00 mtr and one shop of 623×7.m