Project Duration
Stipulated Date of Commencement April 23 2010
Stipulated Date of Completion /
Likely Date of Completion
June 20 2010
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,900,530.00
Awarded for ₹ 1,988,414.00
 
Gallery Image
Contractors
M/s. Kamaxi Constructions
Gallery Image
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Fire fighting, fire alarm and PA System

View Project
Similar Project

750 KVA Diesel Generator work

View Project
Similar Project

Supply and erection of new 11KV line with AB conductor from 33/11KV colony substation to M/s.Rajiv Gandhi Kala Mandir

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.