Project Duration
Stipulated Date of Commencement November 10 2010
Stipulated Date of Completion /
Likely Date of Completion
March 09 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 24,644,210.00
Awarded for ₹ 22,358,766.00
 
Gallery Image
Contractors
M/s. Space N Style
Gallery Image
Consultants
M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.
 
Similar Projects

See Similar Projects

Similar Project

HVAC Work

View Project
Similar Project

Supply, Installation, Testing and Commissioning of street light poles and fixtures along with allied electrical works for the stretch from Odxel junction to GMC

View Project
Similar Project

Construction of a New Wholesale Fish Market at Margao (Phase I – Site Development work).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.