Project Duration
Stipulated Date of Commencement
April 02 2011
Stipulated Date of Completion /
Likely Date of Completion September 01 2011
Likely Date of Completion September 01 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,20,149.00
Awarded for
₹ 27,09,910.00
Contractors
M/s. MDD Medical Systems (I) Pvt. Ltd.
Consultants
Datta Kare Associates