Project Duration
Stipulated Date of Commencement
May 05 2011
Stipulated Date of Completion /
Likely Date of Completion September 04 2011
Likely Date of Completion September 04 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,320,372.00
Awarded for
₹ 2,484,939.25
Contractors
M/s. Eagle Construction Co.
Consultants
Datta Kare Associates