Project Duration
Stipulated Date of Commencement May 05 2011
Stipulated Date of Completion /
Likely Date of Completion
September 04 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,320,372.00
Awarded for ₹ 2,484,939.25
 
Gallery Image
Contractors
M/s. Eagle Construction Co.
Gallery Image
Consultants
Datta Kare Associates
 