Project Duration
Stipulated Date of Commencement
June 22 2011
Stipulated Date of Completion /
Likely Date of Completion October 21 2011
Likely Date of Completion October 21 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,648,277.41
Awarded for
₹ 3,589,980.00
Contractors
M/s. Sombansi Enviro Engg. Pvt. Ltd.
Consultants
M/s. Effective Architectural Services