Project Duration
Stipulated Date of Commencement November 27 2010
Stipulated Date of Completion /
Likely Date of Completion
June 26 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,59,76,814.81
Awarded for ₹ 3,25,13,771.00
 
Gallery Image
Contractors
M/s. Rohini Industrial Electricals Ltd.
Gallery Image
Consultants
M/s. Effective Architectural Services
 
Similar Projects

See Similar Projects

Similar Project

Renovation of Office Premises occupied by the Goa Public Service Commission, EDC House, Panaji

View Project
Similar Project

Interior & Furniture work

View Project
Similar Project

Igreja De Nossa Senhora de Ajuda Church Ribandar- Balance Civil, Electrical & Miscellaenous works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.