Project Duration
Stipulated Date of Commencement
November 27 2010
Stipulated Date of Completion /
Likely Date of Completion June 26 2011
Likely Date of Completion June 26 2011
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,59,76,814.81
Awarded for
₹ 3,25,13,771.00
Contractors
M/s. Rohini Industrial Electricals Ltd.
Consultants
M/s. Effective Architectural Services