Project Duration
Stipulated Date of Commencement
December 21 2012
Stipulated Date of Completion /
Likely Date of Completion April 20 2014
Likely Date of Completion April 20 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 523,561,066.00
Awarded for
₹ 439,700,000.00
Project highlights
400 m long bridge comprises of a main of 80m over the waterway and 10 approach spans of 32 meters each on both sides with girder system.
Contractors
M/s. S. P. Singla Construction Pvt. Ltd..
Consultants
M/s. S. N. Bhobe
See Similar Projects
Dismantling of HT overhead lines and supplying & laying of HT Underground cables at Porvorim
View Project
Improvement / Hot mixing of roads in Arpora – Baga.
View Project
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) -Electrical work
View Project





