Project Duration
Stipulated Date of Commencement October 26 2006
Stipulated Date of Completion /
Likely Date of Completion
February 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,119,623.00
Awarded for ₹ 11,376,000.00
 
Gallery Image
Contractors
M/s. BOC India Limited
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Supplying and laying of 33 KV underground cable from Sub Station to District Hospital at Mapusa

View Project
Similar Project

Construction of 450 bedded Ward Block at GMC Complex, Bambolim, Goa. Civil, Plumbing, Electrical and Fire Fighting work.

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – SH: Reprogramming of Audio Video System installed at Sub-District Hospital, Ponda – Goa.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.